Construction phases of the new Curling Center

Oct 22, 2017 - Before construction
Oct 25, 2017 - Cleaning up the lot
Nov 3, 2017 - Digging for the footing
Nov 10, 2017 - Installing the piles
Nov 17, 2017 - Pouring the concrete
Dec 2, 2017 - Drying up the footing
Dec 9, 2017 - Installing reinforced steel
Dec 23, 2017 - Drying up the foundation
Jan 12, 2018 - Foundation is ready to receive the structure
Feb 2, 2018 - Metal framing is installed for the club house
     
Feb 9, 2018 - Exterior walls are put in place
Feb 23, 2018 - Moving on up to the second floor
March 16, 2018 - The second floor exterior walls are put in place
March 20, 2018 - The trusses are being installed and they're starting on the roofing
May 6, 2018 - The metal roofing is almost completed
May 22, 2018 - Working inside on the main floor
May 22, 2018 - Preparing the ground inside for the ice surface, at the same time
May 22, 2018 - Going up to the second floor
June 19, 2018 - Around the bar